The Grid Is Late.
Your Schedule Isn’t.

Schedule Protection · Lead-Time Intelligence

160+weeks Generator Step-Up TransformersOrder to delivery, Q1 2026
80–210weeks Large Power TransformersRange across substation and GSU classes
~5years Heavy-Frame TurbinesUp to 7 years for new orders
~107weeks Reciprocating GensetsCat 3600 family

2026 market lead times · sources cited in each report · the gap is dead time to be bridged — not a permanent barrier

About the report

Independent Reading.
Disclosed Publisher.

The Power Gap Report tracks the widening space between electricity demand and the grid’s capacity to deliver it — as sourced lead-time data, not opinion.

Every figure we publish is real and traceable to a cited source. We frame the gap the way the data supports it: 12–36 months of dead time on a project schedule — bounded and plannable, never permanent stranding. If you build or operate large electrical loads, the report exists so the gap never surprises your schedule.